扩建工程项目总承包合同(中英文)(doc 26页)内容简介
扩建工程项目总承包合同(中英文)内容提要:
1.1MAIN TECHNICAL PROCESS FLOW CHART
主要工艺流程
LUU XA main plant will adopt a long process production line, namely coke oven, sintering machine, blast furnace, converter, and continuous casting production line.
LUU XA主厂区采用长流程炼焦、烧结、高炉、转炉连铸生产工艺
01# EPC package mainly includes raw material yard project, coke making project (coke oven), sintering project, iron making project, steel making project, and oxygen generating project, whole plant utilities (water, electricity and natural gas) at the second stage and general layout and transportation.
EPC工程包括的主车间:原料场;炼焦(焦炉)工程;烧结工程;炼铁工程;炼钢工程;制氧工程;二期全厂公辅设施(水、电、燃气);总图布置及运输。
1.2CONTENTS OF CONTRACTING
1.3合同内容
The Employer uses the EPC bidding method. The bidding scope includes  main plant area geological exploration for the second stage project, engineering design, equipment supply, staff training, project construction, equipment installation, test-run, trial production, start up of production, acceptance test and hand over.
雇主采用EPC方式招标,其内容包括:主厂区二期的地质勘探;工程设计;设备供货;人员培训;施工;设备安装;试车;试生产;投产;验收交付。
1.4ADOPTED STANDARDS AND CODES
项目规范和标准
According to the requirements of the bidding documents, Vietnam or China standards and codes shall be adopted.
按照招标文件的要求,采用TISCO提供的越南标准和规范,如果TISCO不能提供相关的越南标准和规范,在工程设计、设备制造中将采用中国相应的标准和规范。
1.5PROJECT CONSTRUCTION SHCEDULE
项目实施进度表
The EPC’s contractor shall complete their work within 30 months.
The project construction schedule is arranged based on the actual situations of all the main production lines of second stage revamping and expansion project to meet the requirements of whole project starting production.
承包商应在30个月内完成EPC合同中规定的工作。项目实施进度是根据二期扩建工程各主要生产线在项目整体投产过程中的需要来进行安排。
..............................